Burlington Community School District board meeting, date not confirmed yet
1 h 19 min · 0 public speakers
This board doesn’t post agenda times. Click a board member to jump to where they first speak; we list only members whose voice our check named. Video length 1 h 19 min.
- Who spoke · first speaks at
What happened
What happened at this meeting
Burlington school board approves $48,000 restroom remodel at performing arts center 31:35
- A staff member said the Greyhound Performing Arts Center project was about 40.7% complete according to the schedule. 24:28
- The board approved a restroom remodel tied to the Greyhound Performing Arts Center project after a staff member said the cost had been brought down to a proposed $48,000 from $67,000. 31:50
- The board also approved a special education allowable growth request for $207,097.66. 47:36
- The board approved the first reading of two policies with an amendment and the first reading of the Board Policy 500 series. 1:00:24
Until Nov 4, lines where a board member takes a side don't name the member. Why →
Item by item (15)
- Opening, agenda and public comment 4:54
- Student representative reports 5:37
- Student representatives reported on records and upcoming events for football, volleyball, tennis, cross-country and girls swim. 6:04
- The student representatives described club activities, including homecoming planning by student council and a fall leadership conference trip for DECA. 9:06
- A student representative said the homecoming parade would be Wednesday, September 30th, at 6 PM, with lineup starting at 5. 14:37
- Consent agenda 15:24
- SAVE monthly status report 16:39
- A staff member said the lighting replacement was substantially complete but that some light levels were a few foot candles short of a recommendation, and said safety should not be a concern. 16:57
- The staff member recommended release of retainage for bid package 10, whose contractor did the plumbing and HVAC work and had completed its closeout documentation. 18:51
- The staff member said a 10,000-lumen fixture had been specified but was discontinued, leaving a 7,000-lumen fixture, and that lowering the fixtures was a possible solution. 19:26
- The board approved the report on a motion by Deborah Hatteberg. 24:16
- Performing arts center status report 24:28
- The staff member said installation of precast panels defining the stage area was set to start the next day, weather permitting. 25:19
- The staff member said there were 4 change orders this month totaling about $8,000 and that contingency would likely remain tight throughout the project. 26:19
- A staff member said the project was about 40.7% complete according to the schedule and about 42% complete based on contractor billing, with about 34% of contingency used. 26:44
- The board approved the report on a motion by Deborah Hatteberg. 31:27
- Performing arts center restroom remodel 31:35
- A staff member said the proposed cost was $48,000 compared to $67,000, that demolition would be done over winter break, and that the project bid came in at $9.11 million, about $300,000 under budget. 31:50
- One board member said contingency was tight and that $48,000 seemed like a lot for a bathroom remodel, while another board member said $48,000 was a fairly small percentage compared to $9.1 million. 36:15
- One board member asked that the board soon see the full list of district projects, and a staff member said that was a priority. 41:40
- The motion by Deborah Hatteberg to proceed with the renovation as presented passed. 41:00
- Delegate to state board association assembly 42:44
- Resolution naming depositories 44:07
- A presenter said the district must name depositories annually and that the only changes were name changes, with Two Rivers and Midwest Bank now Nicolette and First Mid. 44:23
- Marlis Robberts asked whether the district could look at local depositories for another year. 44:56
- The resolution passed on a motion by Marlis Robberts. 47:04
- Special education allowable growth request 47:22
- A presenter said the special education deficit this year was roughly about $285,000, with a $70,000 carryover balance, and that the request to the SBRC was for $207,097.66. 47:36
- The presenter said the request does not mean the district is getting cash or raising property taxes. 48:44
- The motion passed. ~50:16
- Vocational rehabilitation contract amendment 50:16
- Area education agency service agreement 52:28
- Graduation fireworks agreement 54:39
- Dance team sharing agreement 55:12
- Item 56:28
- A speaker asked to add language requiring background checks and employment eligibility checks prior to final offer of employment. 58:12
- One board member said being in agreement with the change, and a staff member said it would align with practice. 58:42
- The first reading with the amendment passed on a motion by Marlis Robberts. 1:00:24
- Item 1:00:48
- A staff member said the update was checked against Iowa School Board policy updates and ran 246 pages. 1:01:11
- Marlis Robberts asked for a future agenda item on implementation of the disruptive student policy. 1:02:36
- Tammy Anderson asked how staff are told of policy changes, and a staff member described building visits called a district updates or road show. 1:04:59
- The first reading passed on a motion by Marlis Robberts. 1:07:37