What happened at this meeting
Staff outline plan to bring priced facilities packages to board in December 41:50
- A district staff member presented results of a community facilities survey offered from June to October that drew 136 responses. 1:00
- The staff member said 82% of survey respondents listed critical repairs as their highest need, with safety and CTE in the next tier. 11:50
- Discussion covered options for the middle school, the need for clear cost information and a possible tax calculator tool. 22:55
- A staff member said staff would put together and price packages, bring them to the board in December and likely send them out for broader feedback in January. 41:50
Item by item (11)
- Opening of work session 0:02
- Community facilities survey results 1:00
- A staff member said the survey drew 136 responses and that 35% of respondents were staff, which the staff member called a limitation. 3:17
- The staff member said 76% of respondents were comfortable with an increase of $50 or below. 9:53
- The staff member said 27% of early respondents wanted new construction, compared with 4% in broader community groups. 11:24
- Survey recommendations 13:04
- A staff member recommended a fix-it-first bond package anchored on critical repairs and safety, with CTE included. 14:20
- The staff member also recommended launching a transparency plan with a tax impact calculator, a citizen oversight committee and outreach to every community. 14:50
- The staff member said staff and students repeatedly raised the middle school, and said one idea to move the middle school and build a new high school would cost $130 million. 17:19
- School safety projects 18:59
- Middle school remodel versus replacement 21:55
- A staff member said the long-range facilities plan put a new middle school at around $90 million. 22:04
- Package options and transparency 22:55
- A speaker called for budgeted options for a middle school upgrade, a new middle school and a new high school, with respondents asked about each package. 22:55
- A speaker said people in the community have discussed items from the last bond that did not happen and said the simpler the bond, the better. 26:22
- A speaker said the speaker's top priority included the middle school, the stadium and the facilities office. 28:25
- Seismic review 29:03
- Developing simplified packages 30:00
- Tax impact calculator 33:16
- A speaker described a prototype tool using public tax assessor data to show a property owner's estimated tax increase from a proposed bond. 34:08
- A speaker asked that the tool show the cost per month. 36:01
- A staff member said the average assessed value of a home was $245,000 and noted the district has a facilities conditions landing page on its website. 37:32
- Next steps and community outreach 38:43
- Closing remarks and adjournment 45:33
Written by software from the meeting's transcript and checked sentence by sentence against it.
Who spoke
Who spoke
We can’t yet tell who is speaking at this board’s meetings.
Video: posted by the district as “School Board Work Session - October 20, 2026”