Elizabeth Forward School District committee meeting, date not confirmed yet

1 h 06 min

Click any moment below to jump the video to that second. Video length 1 h 06 min.

This board doesn’t post agenda times.

What happened

What happened at this meeting

Board reviews weapon detection scanners and social media policy options 48:08

  • The board heard a finance committee report covering grants, transportation savings, building spending reports and the future cost of replacing iPads. 17:36
  • A construction update covered new parking, a nearly finished auditorium and change orders for Phase 1 and Phase 2 of the high school project. 36:50
  • The board also reviewed a planned purchase of portable weapon detection systems and a revised social media policy that could close comments on district pages. 48:08
  • No votes were recorded in the transcript. ~1:05:29
Item by item (9)
  1. Opening and superintendent's report 4:34
    • The board met in executive session before the meeting to discuss personnel issues, litigation updates and district safety and security. 5:24
    • The superintendent's report noted that teachers started the school year on August 25th and students on August 31st. 6:02
    • New safety protocols for a home football game included a clear bag policy, no re-entry into the stadium and a requirement that students 13 or under have an adult with them. 6:45
  2. Public comment 5:03
    • A speaker at public comment asked whether an HVAC consultant item covered the same work paid for in January and asked whether hiring extra maintenance staff would cost less than contracted projects. 8:32
    • A district official responded that the consultant item continued an hourly agreement and that maintenance staffing was under discussion. 11:04
  3. Finance committee report 16:28
    • The finance committee report said the district had applied to the state for a $4.5 million public school facilities grant and was awaiting feedback. 17:36
    • The report said consolidating bus runs had produced savings of $205,000, with the potential to approach $300,000. 21:00
    • The report said iPad leases end next year, with about a $1.2 million fund for 4 years, and a speaker noted that devices are required for state testing starting in grade 3. 25:47
  4. Curriculum update and education agenda 28:35
    • An administrator said teachers were implementing new curriculum and that a September newsletter on curriculum updates would go to parents. 28:51
    • Agenda items included a rewrite of the student government constitution, a PSBA policy service agreement and several special education placement agreements. 32:09
    • Other items included attendance at a superintendent's workshop October 7th, 8th, and 9th in Erie and an NCAA eligibility seminar at a cost of $40. 34:23
  5. High school construction update 36:50
    • A presenter said new paving, signage and line painting were complete and that the district ended up with significantly more parking spaces. 36:50
    • The presenter said the auditorium was nearly ready apart from punch list work, with removable seating for the first 2 rows due the first or second week of November. 37:51
    • The presenter described subsurface stormwater detention systems installed as part of the project's NPDES permit. 42:46
  6. Construction change orders 44:03
    • A presenter said a Phase 1 change order would credit $18,000 after a railing was eliminated, and a $8,367 change order for a new auditorium control desk was likely next month. 44:03
    • The presenter said a Phase 2 change order of 28,994.29 would raise a window opening on the existing gym, with Phase 2 change orders at 0.43% of the budget. 45:48
    • The presenter said Phase 1 had $2.63 million remaining in contingency and roughly 1.6% of the budget in change orders. 46:06
  7. Weapon detection systems and facilities items 48:08
    • A district official said the district would purchase 3 sets of portable open gate weapon detection systems and seek funding through a state school safety and mental health grant of just under $200,000, with an October 16th deadline. 48:08
    • Other facilities items included annual bus stop approvals, locker room furniture from WB Mason and a consulting engineering contract for Arc Ultra. 48:08
    • The official said the consulting contract would increase from $18,000 to $24,000. 48:08
  8. Student activities and policy readings 48:08
    • The board reviewed a spring training trip to Florida for softball coaches and players, with the district covering only transportation to and from Pittsburgh International Airport. 53:50
    • Policies for first reading included school visitors, the mission and vision statement and district social media. 55:03
    • A staff member said the social media policy would replace profane with obscene, lewd and vulgar language, and that the board could choose between a designated public forum and a non-public forum without comments. 56:42
  9. Closing remarks and recognitions 1:00:29
    • A speaker thanked staff, contractors and the community for opening the school year during construction. 1:00:42
    • A speaker said a national news story featured the football team's work with a program supporting students. 1:02:23

Written by software from the meeting's transcript and checked sentence by sentence against it.