What happened at this meeting
Red Creek staff reports pool work paused after ventilation failures found 8:57
- The board held roll call votes on a motion on 1 through 7, on a motion on F1, 2, 4, and 5, and on a separate motion on 3. 1:50
- A district staff member told the board that pool work in the capital project was paused after collapsed and structural failures were discovered in ventilation systems under the concrete. 9:27
- The staff member said the fix will exceed the $35,000 change order limit the board authorized, will need board and SED approval, and remains within the project budget. 10:39
Item by item (7)
- Opening and routine approvals 0:00
- Consent agenda 0:00
- New business items 3:38
- A separate motion was then called for on 3, and the roll call drew both yes and no responses. 4:27
- Draft presentation schedule 5:10
- A staff member said the draft schedule puts all 3 building presentations together and keeps 3 formal budget presentations together. 5:25
- The staff member said the board could be asked to do a walkthrough of the capital project in September, before or after the board meeting. 5:55
- The staff member said recognition ceremonies for students would be added as they come up during the year. 6:49
- Capital project update 7:11
- A staff member said paving of the parking lots would start next week, cabinets had gone into 9 elementary classrooms and the other 16 classrooms would get cabinets next week. 7:11
- The staff member said pool work was paused after collapsed and structural failures were found in ventilation systems, and the engineering and architect teams had presented ideas that were not yet finalized. 9:28
- The staff member said the fix would probably be about 10 times the $35,000 change order limit and that the project remains under its $32 million threshold. 10:39
- Vendor and service provider list 13:59
- A staff member said about half of the listed vendors and contracts are grants and the rest are BOCES services on which the district pays about 25 cents on the dollar. 13:59
- A district staff member said the vendors and service providers cover areas such as mental health supports, additional counseling supports, 21st Century after-school programs and summer programs. 13:59
- Board committees and executive session 16:00
Written by software from the meeting's transcript and checked sentence by sentence against it.
Who spoke
Who spoke
We can’t yet tell who is speaking at this board’s meetings.
Video: posted by the district as “Red Creek BOE Meeting, August 5, 2026”