Presenter puts cost of six modular classrooms at Boyertown Elementary at roughly $2.1 million 1:55
- A presenter from CHA described a plan for six permanent modular classrooms at Boyertown Elementary, connected by an enclosed canopy walkway, at roughly $2.1 million in total cost. 1:55
- Questions during the presentation covered leasing versus buying the units, their expected lifespan and parking. ~9:48
- A district official said the board would be asked at a later legislative meeting to consider a design services contract and two change orders. 27:33
- Presenters from KCBA reviewed a study of the baseball stadium and estimated $2 million to $2.4 million for improvements to the bleachers, roof and restrooms. 36:05
Item by item (5)
- Opening and roll call 1:41
- Modular classrooms at Boyertown Elementary 1:55
- The presenter said each of the six classroom modules would have its own HVAC unit and could accommodate up to 30 students, with a total cost of roughly $2.1 million including design fees, permits and contingencies. 8:43
- The presenter said the maximum lease is 60 months at $7,500 per month and estimated a 15 to 20 year lifespan for the trailers. 9:53
- A district official said six classrooms were planned because the need is 5 plus one special, with bidding probably in January and an award in February for summer installation. 20:44
- Design contract and capital project updates 27:33
- The presenter reported a credit change order of a negative $96,323 for the turf field contractor for unused material allowances. 29:01
- The presenter recommended approval of an electrical change order for cabling after the utility asked that a transformer component be relocated outside, and said the project was running under the original budget. 29:01
- Baseball stadium condition study 36:05
- Closing and adjournment 1:04:03
Written by software from the meeting's transcript and checked sentence by sentence against it.
Who spoke
Who spoke
We can’t yet tell who is speaking at this board’s meetings.
Video: posted by the district as “Boyertown Area School Board Facilities Committee Meeting: 10/27/26”